What Is a Double Pole Knife Switch?
A double pole knife switch is an electrical switching device that simultaneously controls two separate circuit conductors using a single mechanical operation — a single handle or pair of linked blades that open and close both poles together, in one motion, every time. It is the two-pole member of the knife switch family: a category of switches defined by the exposed, hinged blade design that has remained the standard for high-current manual isolation switching in industrial, laboratory, and heavy-duty applications for over a century.
Every specific wiring decision covered later in this guide flows directly from understanding how the switch works and why it was designed the way it was.
Double Pole Knife Switch Wiring Diagram
Before connecting a single wire, understanding the wiring diagram for your specific switch type and application is the most important preparation step. A correctly read wiring diagram tells you exactly which terminal connects to which conductor, which conductors bypass the switch entirely, and what the circuit should look like at every point in its path from supply to load. This section covers the diagrams for the most common double pole knife switch installation scenarios.
Basic DPST Knife Switch Wiring Diagram
The fundamental DPST knife switch wiring diagram is built around one central principle: the switch intercepts two conductors simultaneously, breaking both circuit paths when open and completing both when closed.
In its most basic form, the circuit reads as follows for each pole independently — and both poles operate together:
Pole 1: Supply conductor A → Input Terminal 1 (line side) → Blade 1 → Jaw Contact 1 → Output Terminal 1 (load side) → Load conductor A
Pole 2: Supply conductor B → Input Terminal 2 (line side) → Blade 2 → Jaw Contact 2 → Output Terminal 2 (load side) → Load conductor B
Both blades move simultaneously with a single handle operation. Both poles are open together (switch OFF) or closed together (switch ON). There is no independent control of one pole without the other.
In a physical layout, the four terminals of a DPST knife switch are arranged as two pairs: the two input terminals are on the same end of the base (the hinge end, where the blades pivot), and the two output terminals are on the opposite end of the base (the jaw contact end). The two conductors entering the switch from the supply side connect to the two input terminals; the two conductors leaving the switch toward the load connect to the two output terminals. The earth/ground conductor does not pass through the switch — it connects directly from the supply earth to the load's earth terminal, independent of the switching mechanism.
This four-terminal, two-parallel-path layout is the complete DPST wiring diagram. Every DPST double pole knife switch installation — regardless of whether it's a 240V AC circuit, a DC battery system, or a full live-and-neutral AC isolation — follows this same fundamental diagram, with only the labelling of the conductors changing based on the supply type.
How to Identify the Line and Load Terminals
On a double pole knife switch, the four terminals must be correctly identified before wiring — connecting supply conductors to the load terminals (or vice versa) creates a serious safety hazard, as discussed in the common mistakes section.
Method 1: Manufacturer labelling. Most quality knife switches label their terminals directly on the base. Look for markings such as "L1 / L2" (line/supply terminals), "T1 / T2" (load terminals), "LINE" / "LOAD", or simply "IN" / "OUT". These markings are typically moulded into or printed on the insulating base adjacent to each terminal post. If markings are present, use them as your primary reference — but verify against the manufacturer's datasheet to confirm the labelling convention used.
Method 2: Physical inspection of the blade mechanism. The input (line) terminals are always on the same side of the switch as the blade hinges — the fixed pivot points around which the blades rotate. Trace the blade from its free end (which engages the jaw contacts) back to the hinge end (which is connected to the input terminal post). The terminal post at the hinge end = input/line terminal. The terminal post at the jaw contact end = output/load terminal.
For a double pole switch, this means there are two hinge-end terminal posts (the two input terminals, one per pole, on the same side of the base) and two jaw-contact-end terminal posts (the two output terminals, one per pole, on the opposite side of the base).
Method 3: Continuity testing. With the switch in the OPEN position and the supply completely disconnected and de-energized, use a multimeter set to continuity or resistance. Test between each terminal post and the nearest visible blade hinge point. The terminal that shows continuity (near-zero resistance) to a blade hinge is an input terminal. The terminal that shows continuity to a jaw contact assembly is an output terminal. Do not energize the switch for this test — it must be performed with the circuit completely de-energized.
Critical rule for both terminals: The supply (line) conductors must connect to the input terminals — the terminals associated with the blade hinges. This ensures that when the blades are in the open position, the blades themselves are de-energized. If the supply is connected to the output terminals instead, the open blades remain at supply voltage — directly accessible to anyone near the switch — creating a shock hazard that violates NEC 404.6(B) and equivalent international standards.
Double Pole Knife Switch Wiring for AC Circuits
AC circuit wiring for a double pole knife switch varies depending on whether the circuit is a 240V two-hot-wire circuit or a 120V/230V single-phase circuit requiring full live-and-neutral isolation.
240V single-phase circuit (North American standard — two hot conductors):
In a North American 240V single-phase circuit, both supply conductors (L1 and L2) are hot — each carries 120V to earth, and together they provide 240V between them. Neither is a neutral in the usual sense. Both must be switched.
- L1 (typically black wire) → Input Terminal 1 of the knife switch
- L2 (typically red wire) → Input Terminal 2 of the knife switch
- Output Terminal 1 → Hot conductor 1 to the load
- Output Terminal 2 → Hot conductor 2 to the load
- Earth/ground wire → Connected directly from supply earth to load earth terminal, bypassing the switch entirely
When the switch is open, both hot conductors are broken at the switch, and the load is completely de-energized on both supply conductors.
230V single-phase circuit requiring full isolation (live + neutral switched):
In some European, industrial, or laboratory installations, regulations or safety practice requires that both the live (L) and neutral (N) conductors be broken simultaneously for maintenance isolation. A double pole knife switch achieves this:
- Live (L) conductor → Input Terminal 1
- Neutral (N) conductor → Input Terminal 2
- Output Terminal 1 → Live conductor to load
- Output Terminal 2 → Neutral conductor to load
- Protective earth (PE) → Direct from supply earth to load earth, bypassing the switch
When the switch is open, both live and neutral are broken at the switch. The load is completely isolated from both conductors of the supply — no residual live path through the neutral remains, which is the safety advantage of full double pole isolation compared to single pole switching.
Note that in this wiring configuration, the neutral passes through the switch and is subject to the switch's voltage rating and contact quality. The neutral terminal of the switch must be just as well-maintained and correctly torqued as the live terminal.
Earth conductor in all AC configurations: The protective earth (PE) conductor never passes through a knife switch. It must always be connected directly and continuously from the supply earth point to the load's earth terminal — a knife switch's open position must never interrupt the earth continuity. Breaking the earth conductor with a switch is a fundamental wiring fault and a serious safety hazard.
Double Pole Knife Switch Wiring for DC Circuits
DC circuit wiring for a double pole knife switch follows a similar layout to AC, with the supply's positive and negative conductors each assigned to one pole — but with important differences in terminal identification conventions, DC rating requirements, and arc management practices.
Basic DC double pole wiring:
- Positive (+) conductor from DC source → Input Terminal 1
- Negative (−) conductor from DC source → Input Terminal 2
- Output Terminal 1 → Positive conductor to load
- Output Terminal 2 → Negative conductor to load
Both positive and negative are switched simultaneously. When the switch is open, the load is completely isolated from both supply conductors — no residual connection to either the positive or negative rail.
Why both DC conductors should be switched: In a grounded DC system (where the negative conductor is bonded to earth at the supply), switching only the positive conductor would leave the negative rail continuously connected to the load's negative terminal. While this doesn't create an immediate shock hazard in most low-voltage DC systems, it can create subtle ground loop issues, corrosion pathways, and in some system architectures, unexpected fault current paths during maintenance. Switching both conductors provides clean, complete isolation regardless of the system's grounding arrangement.
DC rating verification — the most critical step in DC wiring:
Before connecting any conductor, verify that the knife switch carries explicit DC voltage and current ratings in the manufacturer's datasheet that meet or exceed your circuit's requirements. DC ratings are substantially lower than AC ratings for the same physical switch, because DC arcs — unlike AC arcs — do not self-extinguish at a natural zero crossing. A switch rated 240V AC / 100A may only be rated 48V DC / 60A or 24V DC / 100A.
Using a switch beyond its DC rating risks sustained arcing at the jaw contacts when the blade is opened, potentially leading to contact welding, switch destruction, and arc flash. This risk increases with both voltage and inductance in the DC circuit — a purely resistive DC load at low voltage is relatively forgiving, while an inductive DC motor load at higher voltage (such as in a solar PV system) requires very careful attention to the DC rating.
For solar PV string isolation specifically: the switch's DC voltage rating must meet or exceed the string's maximum open-circuit voltage (Voc), which at standard test conditions is typically 15–25% higher than the nominal string voltage. A 48V nominal system can have a Voc above 60V under cold, high-irradiance conditions — confirm the actual Voc for your specific panel and string configuration and verify the switch's DC voltage rating against that figure, not the nominal system voltage.
Tools and Materials Needed
Gathering the right tools and materials before starting is not just a matter of convenience — it directly affects the quality and safety of the finished installation. A missing tool mid-installation creates pressure to improvise, and improvisation in electrical work is where problems start. Have everything on this list ready and within reach before disconnecting the supply.
Required Electrical Tools
- Voltage tester or digital multimeter.
- Wire strippers.
- Flathead screwdriver.
- Torque screwdriver or torque-limiting driver (strongly recommended).
- Crimping tool (if using ferrules or cable lugs).
- Cable lug crimping tool (for large conductors).
- Needle-nose pliers.
- Lockout hasp and padlock
Recommended Wiring Materials
- Copper conductor wire, correctly rated for your circuit.
- Wire ferrules (for stranded conductors up to approximately 35mm²).
- Cable lugs (for large conductors above 35mm²).
- Cable markers or heat-shrink identification sleeves.
- Insulation tape or heat-shrink tubing.
- Cable ties or cable clamps.
How to Wire a Double Pole Knife Switch Step by Step
With the switch type confirmed, the wiring diagram understood, and the correct tools and materials assembled, you're ready to begin the physical installation. Read through all eight steps before starting — there are points in the sequence where the order of operations matters, and understanding the full procedure in advance prevents the temptation to skip steps when a later step makes the reason for an earlier one clear.
Step 1: Disconnect and Verify the Power
Before touching any terminal, conductor, or component of the circuit, de-energize the supply at its source — not just at a downstream switch or isolator, but at the circuit breaker, fuse, or main isolation point feeding the conductors you'll be working on.
For AC circuits, go to the distribution board and switch off the relevant breaker or remove the relevant fuse. For DC circuits, open the upstream battery disconnect, solar combiner shutoff, or equivalent isolation point. For industrial three-phase supplies, de-energize at the upstream main switch and follow your facility's full lockout/tagout procedure, including obtaining any required work permits.
Once the supply is isolated, verify the de-energization with a test instrument before touching anything. Test at the point where the supply conductors will connect to the switch's input terminals:
- For AC: test between each line conductor and neutral, between each line conductor and earth, and between line conductors. All readings must be zero.
- For DC: test between positive and negative, and between each conductor and earth. All readings must be zero.
If any reading is above zero, stop immediately, return to the supply source, and identify and correct the reason before proceeding. Possible causes include a mislabelled breaker, a circuit fed from an unexpected source, or a multi-source system where only one supply has been isolated.
Apply a lockout hasp and padlock to the isolated breaker or disconnect point after confirming de-energization. If others have access to the panel, attach a warning tag identifying that electrical work is in progress on that circuit. This step prevents accidental re-energization during installation and is mandatory under OSHA 29 CFR 1910.147 for formal industrial work environments — but good practice in any setting.
Step 2: Check the Switch Voltage and Current Ratings
Before mounting the switch or making any connections, confirm that the switch you're about to install is correctly rated for the circuit it will serve. This verification is particularly important for double pole knife switches because both the AC and DC ratings must be checked against the specific circuit type, and because high-current installations sometimes involve switches sourced from stock without individual verification of each unit's specifications.
Voltage rating: The switch's rated voltage must equal or exceed the circuit's supply voltage. For a 240V AC circuit, the switch must be rated at minimum 240V AC. For a 48V DC battery system, the switch must carry an explicit 48V DC rating — not just an AC rating of 240V or higher. Verify both AC and DC ratings
from the manufacturer's datasheet if your circuit could involve either supply type.
Current rating: The switch's continuous current rating must equal or exceed the maximum continuous load current the circuit will carry — including any applicable derating for the installation's ambient temperature and installation method. If the load is 80A continuous, the switch must be rated for at least 80A under your installation's ambient conditions. Check whether the manufacturer specifies a derating factor for elevated temperature — most knife switches are rated at 40°C ambient, and installations in hot environments may require a switch with a higher nominal rating to maintain adequate capacity at operating temperature.
Compare the options in single-throw vs double-throw knife switches.
Utilization category: For AC circuits, verify that the switch's IEC utilization category (AC-21A, AC-22A, or AC-23A) covers the type of load being switched. An AC-21A switch (resistive loads) is not appropriate for switching motor loads — AC-22A or AC-23A is required. The switch's category should be stamped on the base or listed in the datasheet.
If the switch fails any of these checks, do not proceed with installation. Source the correct switch for your application before continuing.
Step 3: Mount the Double Pole Knife Switch
Mount the switch to its panel, backplate, or enclosure in the correct orientation before making any electrical connections. Connecting wires to an unmounted switch and then trying to mount it afterward risks disturbing the connections and makes it much harder to achieve correct terminal torque with the switch in its final position.
Correct mounting orientation: A double pole knife switch must be mounted with the blade hinges at the top and the jaw contacts below, so that gravity acts on the open blades in a direction that keeps them open — not in a direction that would allow them to close under gravity or vibration. This is mandated by NEC Article 404.6(A) and equivalent international standards. The switch base must be mounted perpendicular to the floor — vertical installation, not horizontal.
Fastening procedure: Align the switch base with the mounting holes in the panel or backplate. Insert mounting screws through the base holes and tighten evenly — work diagonally across the base if there are four mounting points, to avoid warping the base material and distorting the blade-to-jaw contact alignment. The base should sit completely flat against the mounting surface with no gaps or rocking at any corner.
After fastening, operate both blades by hand (circuit still completely de-energized) to confirm that the blades move freely and smoothly together, that both blades seat simultaneously and fully in the jaw contacts when closed, and that both blades lift cleanly and simultaneously to the full open position without binding or sticking.
Step 4: Identify the Line and Load Terminals
With the switch mounted and before connecting any wire, confirm the identity of each of the four terminals using the methods described in the wiring diagram section: manufacturer labelling, physical inspection of blade hinge positions, or continuity testing with the circuit de-energized.
The four terminals should be identified as:
- Input Terminal 1 (Line 1 / L1): Supply conductor for Pole 1
- Input Terminal 2 (Line 2 / L2): Supply conductor for Pole 2
- Output Terminal 1 (Load 1 / T1): Load conductor for Pole 1
- Output Terminal 2 (Load 2 / T2): Load conductor for Pole 2
For a correctly oriented switch (hinge at top), Input Terminal 1 and Input Terminal 2 are on the upper side of the switch; Output Terminal 1 and Output Terminal 2 are on the lower side. If there is any remaining uncertainty about terminal identity after applying all three identification methods, consult the manufacturer's datasheet for the exact terminal diagram for your specific switch model before proceeding.
Step 5: Connect the Incoming Power Wires
With the terminal identities confirmed, prepare the supply conductors for termination. Strip the insulation from each conductor end to expose 10–12mm (3/8 to 1/2 inch) of bare copper. For stranded conductors, crimp a correctly sized ferrule onto each stripped end before insertion. For large conductors (16mm² and above), crimp the appropriate cable lug onto each end.
Connect L1 (or positive, for DC) to Input Terminal 1. Insert the stripped end or ferrule fully into the terminal — the bare conductor must be completely captured under the terminal clamp, with no bare metal extending beyond the terminal boundary and no insulation caught under the clamping surface. Tighten the terminal screw to the manufacturer's specified torque. Perform a firm tug test on the wire — it must be completely immovable.
Connect L2 (or negative, for DC) to Input Terminal 2 using identical procedure, to identical torque. Both input terminal connections must be equally well-secured — an asymmetry in terminal torque between the two poles creates an asymmetry in contact resistance that will manifest as unequal heating of the two poles under load.
After completing both input connections, verify visually: no bare copper outside the terminal clamping area on either pole; no insulation pinched under either terminal screw; both conductors seated fully and straight into their respective terminals.
Step 6: Connect the Load Wires
With the supply conductors secured at the input terminals, connect the load conductors to the output terminals using the identical procedure and torque specification.
Connect the load conductor for Pole 1 to Output Terminal 1. This is the conductor that runs from the switch to the live (or positive) terminal of the load — the motor, appliance, distribution panel, or device being switched.
Connect the load conductor for Pole 2 to Output Terminal 2. This is the conductor running from the switch to the neutral (or negative) terminal of the load, or to the second hot conductor terminal of the load in a 240V circuit.
Run the earth/ground conductor. The protective earth conductor must run directly from the supply earth point to the load's earth terminal without passing through the knife switch. Terminate the earth conductor at both ends and verify earth continuity with a multimeter — the reading should be very low (typically below 1 ohm for most installation lengths), confirming a solid, continuous earth connection.
Do a final visual inspection of the complete switch assembly: all four terminal screws fully tightened, all conductors correctly seated, no stray wire strands contacting adjacent terminals or exposed metalwork, and the inter-pole insulating barrier fully intact and undamaged.
Step 7: Tighten and Inspect All Connections
A dedicated tightening and inspection step — distinct from the per-connection checks during Steps 5 and 6 — is where you go back over every connection with fresh attention, specifically looking for anything the distraction of the connection process itself might have caused you to miss.
Re-apply the torque specification to each of the four terminal screws in sequence. Even if you tightened each one correctly during the connection steps, a second torque application after all wires are in place sometimes reveals a terminal that has backed off slightly as the conductor settled into position. This is particularly common with stranded conductors without ferrules.
Perform the tug test on all four conductors. Grasp each wire within 50mm of the terminal and pull firmly — none should move. Inspect the inter-pole insulating barrier for any damage: cracks, chips, or conductor insulation routed over rather than around the barrier. The barrier must be completely intact and must not be bridged by any wire, bare conductor, or conductive material.
Confirm that no bare conductor, wire end, or tool has been left inside the switch enclosure or panel. A dropped screw, a clipped wire tip, or a piece of stripped insulation left inside an enclosure can cause a fault when the circuit is energized.
Review the selection considerations in selecting a knife switch for an electrical panel.
Step 8: Test the Knife Switch Before Energizing
Before restoring supply power, perform a series of de-energized tests that verify the installation is correct. These tests catch wiring errors before the circuit is live — when correction is straightforward — rather than after, when a wiring error may manifest as a fault or equipment damage.
Test 1 — Blade operation. With all wires connected but the circuit still de-energized, operate the blades through several full open-and-close cycles by hand. Both blades must move together simultaneously in both directions. The closed position must feel definite and positive — both blades fully seated. The open position must be clearly open — both blades fully lifted with no possibility of incidental contact.
Test 2 — Pole continuity check. Set the switch to OPEN. Using a multimeter set to resistance or continuity, test between Input Terminal 1 and Output Terminal 1 — the reading must be open circuit. Test between Input Terminal 2 and Output Terminal 2 — also open circuit. Now close the switch. Both pole pairs must now show very low resistance, confirming both poles are conducting correctly.
Test 3 — No inter-pole short. With the switch in any position, test between Input Terminal 1 and Input Terminal 2, and between Output Terminal 1 and Output Terminal 2. Both readings must show open circuit — no continuity between the two poles at any point. Any continuity between poles indicates either a wiring error or damage to the inter-pole insulating barrier, either of which must be corrected before energization.
Test 4 — Earth continuity. Test between the supply earth point and the load's earth terminal. Confirm very low resistance as noted in Step 6.
Once all four tests pass, the installation is ready for energization. Set the switch blades to the OPEN position before restoring supply power — this ensures the load remains de-energized when power is first restored, allowing you to complete the voltage tests described in the following section before the load is connected.
Frequently Asked Questions About Double Pole Knife Switch Wiring
How Many Terminals Does a Double Pole Knife Switch Have?
A double pole single throw (DPST) knife switch has exactly four terminals: two input terminals (one per pole, on the supply/line side of the switch) and two output terminals (one per pole, on the load side of the switch). Terminal count is the fastest and most reliable physical method for identifying a double pole switch type — count the posts on the base before assuming the switch type from any other characteristic.
A double pole double throw (DPDT) knife switch has six terminals: two input terminals (one per pole, at the blade hinge end) and four output terminals (two per pole — one for each throw direction). If you count six terminals on your switch, it is a DPDT model and requires a DPDT wiring diagram, regardless of what the label says.
In both cases, the earth/ground conductor does not connect to any of these terminals — it bypasses the knife switch entirely and connects directly from the supply earth point to the load's earth terminal.
Can a Double Pole Knife Switch Disconnect Two Hot Wires?
Yes — and this is one of the primary reasons a double pole knife switch is specified instead of a single pole switch. In a North American 240V single-phase circuit, both supply conductors (L1 and L2) are hot — each carries 120V to earth, and 240V between them. Neither is a neutral. Both must be simultaneously disconnected for the load to be completely de-energized.
A double pole knife switch handles this by assigning L1 to one pole and L2 to the other. When the switch is opened, both hot conductors are broken simultaneously by the mechanically linked blade mechanism, removing all supply voltage from the load terminals at the same time. This is not achievable with a single pole knife switch, which only breaks one conductor.
Common applications for this two-hot-wire disconnection include 240V electric dryer and range disconnects, 240V air conditioning disconnect switches, 240V water heater isolators, and sub-panel or distribution board main disconnects in 240V installations.
Can a Double Pole Knife Switch Switch Both Live and Neutral Conductors?
Yes. In AC installations where full isolation of the load from both the live and neutral conductors is required — rather than just breaking the live conductor — a double pole knife switch can be wired with the live conductor through one pole and the neutral conductor through the other. When the switch opens, both the live and neutral are simultaneously broken, completely isolating the load from both sides of the supply.
This configuration is used in certain European industrial installations, laboratory settings where complete two-conductor isolation is a safety requirement, and any application where code or safety practice specifies that neutral switching is required alongside live switching.
One important note: when the neutral conductor passes through a knife switch terminal, that terminal must be treated with the same care as the live terminal — same torque specification, same connection quality, same periodic inspection. A loose neutral connection in a switch carrying both live and neutral creates exactly the same overheating and contact failure risk as a loose live connection.
The protective earth conductor (PE) must never be switched — it must remain continuously connected from the supply earth to the load regardless of the knife switch position. Breaking the earth continuity with a switch is a fundamental wiring fault.
Can I Use a Double Pole Knife Switch for DC Power?
Yes, but with one critical precondition: the switch must carry explicit DC voltage and current ratings in its manufacturer's datasheet that meet or exceed your specific DC circuit's requirements. DC ratings for a knife switch are significantly lower than its AC ratings, because DC arcs — unlike AC arcs — do not self-extinguish at a natural voltage zero crossing and must be physically extinguished by the increasing gap between blade and jaw contacts as the blade lifts.
A switch rated 240V AC / 100A might be rated only 48V DC / 60A, 24V DC / 100A, or some other combination. These specific DC values must be documented in the manufacturer's datasheet — do not assume or calculate DC ratings from AC ratings using any conversion formula. If a switch's documentation does not include DC ratings, treat it as unsuitable for DC load-break switching and source a switch with documented DC ratings.
For double pole DC switching, assign the positive conductor to one pole and the negative conductor to the other. Both conductors are switched simultaneously, completely isolating the load from both rails of the DC supply. For battery systems and solar PV, always verify the DC voltage rating against the maximum open-circuit voltage of the source — which for PV systems can be 15–25% higher than the nominal system voltage under cold, high-irradiance conditions.
Can a Double Pole Knife Switch Replace a Circuit Breaker?
No — and this is an important distinction. A knife switch and a circuit breaker serve fundamentally different protective functions, and one cannot be substituted for the other.
A circuit breaker is a protective device designed to automatically interrupt fault current — detecting overload or short-circuit conditions and opening its contacts to clear the fault before conductors and equipment are damaged. A circuit breaker can safely interrupt many times its rated current during a fault, and it resets for continued service or trips permanently depending on the fault severity.
A knife switch is a manual switching and isolation device. It has no automatic fault detection capability and no ability to safely interrupt short-circuit current. Asking a knife switch to clear a short circuit will, in most cases, result in sustained arcing at the blade-to-jaw contacts that damages or destroys the switch — and potentially causes arc flash, fire, or both — rather than safely clearing the fault.
A knife switch can, in appropriate applications, serve as a manual disconnect means — the device that allows a human operator to intentionally de-energize a circuit for maintenance — provided that the circuit has appropriate upstream overcurrent protection that will clear any fault condition before the switch is damaged. The knife switch provides isolation; the circuit breaker (or fuse) provides fault protection. Both are necessary; neither substitutes for the other.
Should the Power Supply Be Connected to the Blade Side or Contact Side?
The power supply must always be connected to the blade side — specifically to the input terminals on the blade hinge end of the switch. This is not a convention or a preference; it is a safety requirement specified in NEC Article 404.6(B) and equivalent international standards.
The reason is straightforward: when the blade is in the open position, it is physically exposed and potentially accessible to anyone near the switch. If the supply is connected to the blade hinge end (the input terminals), the open blade is de-energized — it is connected to the load side only, and the load side is isolated from the supply by the gap between the blade tip and the jaw contacts. If the supply were connected to the jaw contact end (the output terminals) instead, the open blade would be live at supply voltage — a direct shock hazard from a component that is intentionally designed to be visible and approachable.
For a double pole knife switch in its correct mounting orientation (hinges at top), the input terminals are the upper terminals. The supply conductors connect to the upper terminals; the load conductors connect to the lower terminals. Verify this assignment against the manufacturer's datasheet and by physically tracing the blade mechanism before connecting any conductor.